The section of the pulling-correct apparatus of the CCM - 2
At the CSCD facility No. 2 (continuous steel casting department No. 2), construction company “Olvia” performed:
- Detailed design documentation based on detailed engineering from SMS group S.p.A.
- Installation of basic technological equipment
- Installation of process pipelines and hydraulic pipelines
- Installation of electrical equipment and automation systems
- Laying cable lines
- Flushing pipelines
- The whole range of commissioning.
Installation of equipment for the cooling plant CCM-2
To implement this project within the time specified by the customer (6 months), a large engineering work was carried out in all directions with the development of technological maps for all types of work. Teams were correctly formed in all divisions that ensured the coordinated work and implementation of this project.
For the installation of equipment and flushing of hydraulic and lubrication pipelines, detailed technological maps have been developed.
Installation of metal structures of the casting area CCM-2
According to the specified requirements from the equipment manufacturer, drawings were developed and 4 special washing stations were manufactured using instruments for express analysis of cleanliness and washing class.
Construction company "Olvia" at the CSCD facility No. 2 installed and laid:
- 1139 tons of technological equipment SMS group S.p.A.
- 8,086 km of hydraulic and lubrication pipelines
- 3.570 tons of technological metal structures
- 186.6 km of cable lines