Forest Hill is the greenest residential complex in Dnipro city! Eight 6-8 story sections for 253 apartments, as well as thirty-eight 2-3 story townhouses, are being erected on a 3.5-hectare site.
The complex is located in an ecologically clean area with a developed social and transport infrastructure. The Bohdan Khmelnitsky park, Pisarzhevsky park and the Green Small forest park, the Olympic Reserves stadium, the “Dafi shopping and entertainment complex” and the “Apollo shopping and entertainment complex” are located within walking distance.
As of February 24, 2022, due to martial law, the construction company "Olvia" suspended work on the site. As of March 12, 2022, work was resumed.
The complex is located near the main thoroughfares of the city and allows you to always be in the center of business and cultural life.
Construction technology:
- Pile field
- Monolithic grillages and basement floors
- Brick walls made of monolithic silicate bricks 380 mm
- Precast concrete floor slabs
- Insulation - non-combustible stone wool slabs 150 mm
- Ventilated façade with large-format porcelain stoneware tiles
- Double-chamber windows
- Individual double-circuit gas boilers
- Individual places on the facade of the building for the installation of air conditioners
Construction site report as of August 31, 2022.
Block 1 - section 1:
Works on installation of windows, glazing and installation of ventilated facades, and insulation of the parapet from the inside are being carried out.
Internal works: work on the installation of ventilation and air conditioning systems is being carried out, coaxial chimneys have been installed, cable routes for lighting and power supply are being laid, and work is also being carried out on the laying of gas supply networks in apartments. The work on the installation of screeds from the 8th to the 2nd floor is being carried out, and the work on the installation of screeds on the 1st floor is being completed. Installation of elevator equipment is underway.
Block 1 - section 2:
Installation of windows and glazing is underway.
Internal work: work is underway on laying heating and ventilation networks, water supply and sewerage, and radiators are being installed in apartments. Cable routes for lighting, electricity supply, and the Internet are being laid. The screeds are made in full. Installation of elevator equipment is underway. Work is being carried out on the interior decoration of the walls of common areas of use.
Block 1 – section 3:
Installation of windows and glazing is in progress. Roofing works are being completed.
Internal works: work is underway on laying heating and ventilation networks, coaxial chimneys are installed, and lighting and power supply cable routes are laid. Works on the installation of gas pipes and interior decoration of the walls of common areas of use are being carried out.
Block 1 - section 4:
Works on installation of windows, glazing, and installation of ventilated facades are being carried out. Finished work on the arrangement of the roof.
Internal works: work is underway on laying heating and ventilation networks, coaxial chimneys are mounted, and cable routes for lighting and power supply are laid. The screeds are made from the 2nd to the 6th floor in full. Work is underway on the arrangement of screeds on the 1st floor.
Block 2 - section 1:
The work on arranging the ceiling of the 6th floor has been completed. Work is being carried out on the brickwork of the walls leading to the roof.
Internal works: work is underway on laying heating and ventilation networks, and the laying of lighting and power supply cable routes.
Block 2 - section 2:
The work on the arrangement of the ceiling of the 5th floor has been completed. They are carrying out work on the brickwork of the walls of the 6th floor.
Internal works: work is underway on laying heating and ventilation networks, and the laying of lighting and power supply cable routes.
Block 2 - section 3:
Finishing work on the brickwork of the walls of the 6th floor. Work on the arrangement of the monolithic ceiling of the 6th floor begins.
Internal work: work is underway on laying heating and ventilation networks, water supply and sewerage, and laying cable routes for lighting and power supply.
Block 2 - section 4:
The work on the brickwork of the walls of the 4th floor has been completed, and the work on the arrangement of the floor of the 4th floor is underway.
Internal work: work is underway on laying heating and ventilation networks, water supply and sewerage, laying cable routes for lighting and power supply
Block 3 section 1:
The work on the arrangement of monolithic columns has been completed, and the work on the arrangement of the terraces is being completed.
Block 3 section 2:
Work is underway to install a monolithic floor on the 1st floor.
Block 3 section 3:
Work on the arrangement of monolithic terraces has been completed.
Block 3 section 4:
Completed work on the arrangement of the monolithic floor of the 2nd floor and work on the installation of monolithic columns of the 2nd floor. Work is underway to install monolithic parapets.
Block 4 section 1:
Performed work on the arrangement of walls below ground level. Work on backfilling of the soil under the floor was completed, and a monolithic floor was made. Work is underway to install monolithic columns.
Block 4 section 2:
The installation of the monolithic columns of the 1st floor has been completed. They also completed the installation of the monolithic floor of the 1st floor and the monolithic columns of the 2nd floor. Work on the arrangement of monolithic terraces is being completed.
Block 4 section 3:
Backfilling of the soil around the section has been completed.
Block 4 section 4:
Installation of monolithic columns, terraces, 1st-floor ceiling, and monolithic columns of the 2nd floor has been completed. Work has begun on the arrangement of the monolithic floor of the 2nd floor.
Parking lot:
Work is underway to construct a pit for parking lot No. 2. Work is underway to arrange the foundation slab of the parking lot.
Internal networks of the complex:
Work continues on the laying of water supply networks, rainwater, and domestic sewage. Work on the arrangement of the foundation of the transformer substation has been completed, and work on the arrangement of the brick walls of the transformer substation is underway.
External networks of the complex:
Works on laying pipes of external network B1 on the territory of the park have been completed.
Let us also remind you that the Department of Capital Construction of the Dnipropetrovsk Regional State Administration plans to reconstruct the park of Bohdan Khmelnitsky.