The construction company Olvia carries out site preparation works as part of the project implementation: New construction of a complex for thickening enrichment waste on the industrial territory of PJSC SevGOK.
Construction company Olvia performed at the facility:
- Development and removal of unsuitable soil;
- Development of pit from slag;
- Installation of rock slope loading;
- Construction of a temporary access road;
- Setting up a storage area;
- Installation of walls from galvanized profiled sheet;
- Production and installation of metal structures;
- Dismantling of technological pipelines;
- Laying process water pipes with a diameter of 1200 mm;
- Laying of pulp pipes, polyethylene pipes of hydraulic support;
- Backfilling of pit pits, arrangement of foundations for foundations and floors.
During the implementation of the project, specialists of the Olvia construction company received positive feedback from the management of labor protection, industrial safety and ecology of Metinvest-Engineering LLC. More details by link.
Complex construction is a rational approach to the use of energy resources and land for production. As a result of the reduction of electricity consumption for pulp pumping by up to 50%, PJSC SevGOK will reduce the cost of concentrate, which will allow the plant to be more profitable and to further invest in modernization and improve working conditions.